Instructions for Installing a Slip Joint

LaserLock™ Slip Joint telescopes in length to eliminate wasted parts due to improper measurements.

 

Ducting Installation 1
Measure the distance to be spanned.
Ducting Installation 2
Mark pipe approximately
4” more than the distance needed.
Ducting Installation 3

Mark for cutting.
Ducting Installation 4

Drill access hole, then cut
with metal snips or saw along line,
then remove burrs.
Ducting Installation 5

Put O-ring on cut pipe.
Slide slip joint over cut end of pipe.
Ducting Installation 6

Adjust its length.
Snap clamp over O-ring and
one end of slip joint.
Ducting Installation 7
Insert slip joint assembly
to complete connection.

Back to Top

Instructions for Installing a Ducting Line

LaserLock™ Slip Joint telescopes in length to eliminate wasted parts due to improper measurements.

 

Duct Assembly 1
Connect all 45° branch pieces and
45° elbows to produce a required
90° angle. Lay out branch and elbow
assemblies on the floor in line
with machine entry points
as shown at left.
Duct Assembly 2
Connect the branches to ducting
sections of the correct length and
diameter. Adjustment to length on
duct sections is achieved by using
LaserLock™ slip joint assembly
instructions described HERE.
Duct Assembly 3
Carefully raise main or sub-main to
required center line height above
floor using preferred LaserLock™
hanging material listed HERE.
Duct Assembly 4
Extend branch arms to machines
using correct length and diameter
duct. Adjustment to length of duct
sections is achieved by using
LaserLock™ slip joint assembly
instructions HERE.
Fit another 90° elbow on end of
each horizontal run.
Duct Assembly 5
Install vertical risers from machines
to horizontal runs using your
preferred method of connection.
Duct Assembly 6
Connect main or sub-main to filter,
fan or desired machinery with
required standard or custom fitting
manufactured by Duct Incorporated,
or continue with next section of system.

Back to Top